Composting facility

Building owner:

Tricomix SA, Via ala Capelina, 6593 Cadenazzo

Contacts:

Contact: Mr Rino Bassi

Function: Building owner

Phone: +41 (0)91 858 32 69

E-Mail: This email address is being protected from spambots. You need JavaScript enabled to view it.

 

Composting facility

Mission:

Planning and implementation of the turnkey facility System Compag

Construction time:

6 months

Figures:

Investment costs included building construction: CHF 2,75 Mio.

Capacity: 12'000 tons per year

Commissioning: 12/2012

Input: green waste 

Process engineering: Covered composting facility System COMPAG

Systems engineering: Covered composting facility with pressure ventilation